4. Demand intake and prioritization

In a large automotive OEM, a CAE portfolio rarely fails because of insufficient solver capacity. It fails because the wrong analyses get run first. Demand intake and prioritization is the discipline that converts a noisy stream of program requests — crash load cases, NVH targets, thermal duty cycles, durability road profiles — into a ranked, defensible queue that matches engineering value to available analyst hours. This chapter covers how to capture requests consistently, how to score them, and how to resolve the conflicts that inevitably surface when three vehicle programs want the same crash team in the same week.

Why Ad-Hoc Intake Breaks Down

When requests arrive by email, chat, or hallway conversation, three failure modes appear. First, incomplete requests: an NVH engineer asks for "a body-in-white modal analysis" without specifying the trimmed vs. untrimmed condition, frequency band, or boundary constraints, so the analyst either guesses or bounces it back. Second, invisible demand: work that was never formally logged consumes capacity but never appears in utilization reports, so planning is systematically optimistic. Third, priority inflation: every requester marks their item "critical," which collapses the ranking into a first-come-first-served queue driven by whoever escalates loudest.

A structured intake process fixes all three by forcing a minimum information set, creating a single visible backlog, and applying a scoring rule that is applied identically to every request.

The Intake Record: Minimum Required Fields

Every CAE request should be captured as a structured record before it enters the backlog. The fields below are the minimum that allow an analyst to estimate effort and a planner to rank without a follow-up meeting.

Field Purpose Example value
Request ID Unique traceability key CAE-2024-0417
Program / Platform Links demand to vehicle line B-SUV / Platform P2
Requester & stakeholder Accountability and sign-off Body Structures Lead
Analysis type Drives method and solver Full-vehicle frontal crash, 50 km/h ODB
Model / data maturity Determines readiness CAD freeze B, mesh 80% complete
Decision it informs Connects work to a gate Design freeze sign-off, Gate DF3
Required date Drives urgency 2024-06-14
Estimated effort Drives capacity load 6 analyst-days

The "decision it informs" field is the most important and the most frequently omitted. A CAE result that does not feed a specific engineering decision — a gate review, a design change, a supplier selection — is a candidate for deferral. Requiring requesters to name the decision filters out exploratory work that belongs in a research budget, not the program backlog.

Scoring by Impact and Urgency

With records captured, ranking uses two independent axes. Impact measures how much the result changes a decision; urgency measures how soon the decision must be made. Keeping them separate prevents the common error of treating "due soon" as "important."

A practical impact score (1–5) can be built from three sub-factors:

  • Decision leverage — does the result gate a design freeze (5), inform a trade study (3), or provide background data (1)?
  • Program exposure — how many vehicles or variants depend on the outcome? A platform-wide result outranks a single-variant check.
  • Risk of being wrong — safety, regulatory, or cost exposure if the design passes CAE but fails physical test.

Urgency (1–5) is driven by the gap between the required date and the earliest date the analysis can physically start, given model readiness. A request due in three weeks whose model will not be meshed for two weeks has low effective urgency regardless of the calendar.

Priority Index = Impact × Urgency, with a tie-breaker on the shorter slack (required date minus earliest feasible completion). This produces a 1–25 scale that is transparent and auditable.

Consider three competing requests in the same week for a single crash analyst:

Request Impact Urgency Index Slack (days)
CAE-2024-0417 (frontal ODB, gate DF3) 5 4 20 9
CAE-2024-0421 (rear impact, trade study) 3 5 15 4
CAE-2024-0425 (roof crush, background) 1 2 2 30

The frontal ODB request wins on index despite lower urgency, because it gates a design freeze. The rear-impact request has the tightest slack and should be flagged for a capacity decision — either pull a second analyst or negotiate the date — rather than silently displacing the higher-impact work.

CAE Demand Intake and Prioritization Pipeline 1. Capture Structured request record Program, analysis type, decision, required date Reject if decision unnamed 2. Readiness Check CAD freeze status Mesh completion % Earliest feasible start Blocked → hold queue 3. Score Impact (1–5) Urgency (1–5) Index = Impact × Urgency Tie-break on slack 4. Ranked Backlog Single visible queue Capacity-matched Weekly review Re-scoring when model readiness or gate dates change Capacity Conflict Resolution When two requests exceed available analyst-days, compare Priority Index first, then slack. Options: (a) defer lower-index work, (b) reallocate from non-program budget, (c) negotiate the gate date. Never resolve by escalation volume — that reintroduces priority inflation.

Resolving Capacity Conflicts

Scoring produces a ranked list, but the list must be reconciled against real capacity. A crash analyst who can deliver roughly 1.5 full-vehicle models per month cannot absorb four simultaneous gate-driven requests. The weekly portfolio review should compare the ranked backlog against a capacity model expressed in analyst-days per skill group — crash, NVH, thermal, durability, CFD — because these skills are not interchangeable.

When demand exceeds capacity, three legitimate moves exist. Defer the lowest-index request and communicate the new date to the requester immediately. Reallocate from a non-program or research budget if the work has strategic value. Negotiate the gate date with the program, which is a program-management decision, not a CAE decision. What must not happen is silent overload, where analysts absorb the excess through overtime and the backlog becomes fiction.

Common failure symptom: the backlog shows 12 open requests but analysts report working on 20. This means requests are bypassing intake. Audit by comparing the request log against actual solver job submissions — every job should trace to a request ID. Untraceable jobs indicate shadow demand that must be captured or stopped.

Making the Process Stick

Intake discipline survives only if it is faster than the informal alternative. Keep the request form to the eight fields above, allow submission through a lightweight web form or shared tracker, and publish the ranked backlog weekly so requesters can see where they stand. When a requester asks "why is my item below that one?", the answer should be a visible index and slack value, not a judgment call. That transparency is what converts prioritization from a political exercise into an engineering one.

Finally, review the scoring calibration quarterly. If every request scores 20+, the impact scale is too generous. If nothing ever scores above 10, the urgency definition is too strict. The goal is a distribution that meaningfully separates work, so that the top of the queue genuinely represents the analyses that most change vehicle decisions.